Project brief

This project was for the conversion of the existing school under croft into new classrooms along with the creation of a new toilet block and the associated full refurbishment and overhaul to all the existing windows in the main school building.

At the start of the project, we carried out a complete strip out of the building to allow excavation and foundation works followed by concrete pouring. Our construction team installed new partitions, ceilings, dry lining, completed plastering finishes and tiling. New internal doors were installed as well as underfloor heating and replacement flooring. All mechanical and electrical systems were installed, commissioned, and tested by our M&E Division.

Externally, we created a new paved and landscaped area for the children to enjoy.